SAFER ISOLATIONS – WESSEX CTS

As part of Network Rails Safer Isolations in and around Wessex, several alterations to track feeds were required to be undertaken to allow for safer isolations.  A number of the equipment locations required civil design and input at AIP and detailed designs stages.

 

“Through the way that AJMS manage their projects it is clear that they strive to achieve customer satisfaction and I believe they succeed in this. All members of the team are approachable, experienced and competent in their work, and I would highly recommend them.”
Lewis Hipwell (Construction CRE)

 

PROJECT SCOPE AND DELIVERY

The Controlled Track Switches allow the disconnection of the DC power supply to the conductor rail to be undertaken remotely from the Electrical Control Room (ECR) removing the requirement for persons to manually operate a Hook Switch – Track Isolation Switch (TIS) at trackside. This makes isolation safer for all personnel.
The project identified locations within the Wessex area where new track feeding and equipment were required.


The particular site at Woking had several hazards and CDM issues. The topography for the CTS cabinets meant the equipment was on a steep embankment. For operational safety a staging was required for access in the cess of the No.2 Down Sidings at Woking.
AJMS implementation of Safety by design provided full mitigation.


As part of the initial review, it was identified that earthing and touch potential for the equipment to the traditional steel stagings would be an issue due to the several electrical restrictions in the DC area. Constructability on a steep embankment was also highlighted as a risk. Therefore, AJMS prepared to design and analysis for piled foundations installed from cess level and a polymer/GRP staging to negate any earthing/touch potential issue with the Equipment to the staging.

Client:
Kier
Value:
£100k
Duration:
08/2018 - 10/2019

©2021 AJMS Consultant. All rights reserved | Terms and Conditions | Privacy Policy